Forest Lake Reconstruction Project


On this page you'll find frequent updates about the Forest Lake Estates Reconstruction Project, including photos, traffic plans and additional information. Don't hesitate to call us at (903) 798-3948 if you have specific questions. 

June 13, 2017-
Contractors are working on Phase I subgrade improvements on southbound section of Lakeridge Drive at this time. We are undercutting 18" of the unsuitable subgrade and replacing it with 18" of select fill placed on top of a geosynthetic pavement material to help stabilize the subgrade. Concrete crews should be mobilizing in the next few weeks to start installing forms and laying concrete. 

Forest Lake Estates 4

  Forest Lake Estates Reconstruction
Forest Lake Estates Reconstruction
Forest Lake Estates reconstruction

 May 18, 2017- 
Contractors are still working on removing the concrete on Lakeridge Drive. You can access the contractor's schedule here. Here's a few photos of recent work: 
IMG_0728

IMG_0757

IMG_0758

IMG_0759

IMG_0760


May 11, 2017-

Please see the construction schedule above for estimated dates.

May 3, 2017- 
The concrete crusher is on site today busting up the old concrete to make way for reconstruction. The crusher will complete much of the crushing today on Treasure Hill, Wood Bridge and Ridgecrest (rain or shine). Did you realize the concrete crusher does not have a driver? The operator uses a remote control to guide the piece of machinery. 

Check out the crusher in action! 

May 1, 2017- 
Construction crews will begin removing existing concrete today to prepare for improvements. Work will begin on Lakeridge, and the side streets in that area, and move from north to south. Forest Lake will be the last street where concrete will be crushed and removed. 

April 27, 2017- 

This project will consist of reconstructing all the concrete streets, over 1.5 miles, in the Forest Lake Estates area. Included in this project will be reconstructing the base underneath the pavement with lime stabilization, and in some cases, may include excavating out the unsuitable material and replacing it with select fill. The portion of Forest Lake Drive will be 8” of reinforced concrete, and all other streets will be 6.5” reinforced concrete.

Estimated construction start date is May 1, 2017, and estimated completion date is August 31, 2018. Construction will be split in 3 phases.

  • Phase 1 will be the construction of Lakeridge Drive, Treasure Hill Road, Wood Bridge Drive, and Ridgecrest Place
  • Phase 2 will be the construction of Forest Lake Drive from Lakeridge Drive to the RR Tracks 
  • Phase 3 will be the construction of Forest Lake Drive from the RR Tracks to Highway 71

Residents will have access to their properties throughout construction, but portions of the roadways will be closed as well. Please refer to all road construction and detour signage.


Click here to sign up for email updates and be kept up-to-date on Forest Lake Estates Reconstruction Information